Source Extra

NEW RP – 118R-21: Cost Risk Analysis and Contingency Determination Using Estimate Ranging for Inherent Risks with Monte Carlo Simulation

This recommended practice (RP) defines general practices and considerations for inherent cost risk analysis and estimating contingency using a cost estimate ranging analysis with the Monte Carlo simulation (MCS) method. The method is only recommended for quantifying inherent cost uncertainty when the project scope is well-defined (i.e., Class 3 or better) and when the project has no new technology and minimal complexity. In all cases, the method is not to be used alone when there are significant project-specific risks (e.g., contingent risks or events). The method is applicable to two situations:

  • As the sole method for cost contingency determination (e.g., a small project for an owner or a contractor bid estimate for a simple project when the owner retains responsibility for most scope and event risks).
  • As part of a hybrid approach that uses this RP for inherent cost uncertainty and the expected value method to quantify project-specific cost risks (i.e., contingent risks or risk events).

A key principle for recommended quantitative risk analysis (QRA) methods is that they be risk-driven; i.e., clearly link the risk to the impacts. Estimate ranging using subjective team inputs from those involved in the project design, planning, and estimating can be expected to reliably capture the inherent cost uncertainties.

Estimate ranging does not meet the risk-driven principle when systemic and project-specific risks are significant. In particular, it is not recommended when the project scope is not well-defined (i.e., Class 10, 5, or 4), or the project has technology uncertainty, or any significant level of physical and/or execution complexity. Additionally, when there are significant project-specific risks (the main source of schedule delays as well), estimate ranging cannot be said to clearly link these defined risks to their impacts.

In both situations, estimate ranging tends to underestimate contingency, often by significant amounts. Alternative methods for these situations of greater uncertainty and risks are described in Professional Guidance Document PGD-02, Guide to Quantitative Risk Analysis. RP 41R-08, Understanding Estimate Ranging broadly describes the class of QRA methods called estimate ranging.

In general, estimate ranging methods with MCS replace fixed values in a cost estimate with 3-point or uniform distributions, establish correlations between the distributions, and running MCS to obtain an overall cost outcome distribution. There are many variations possible within this general description. For example, the fixed values replaced could be for individual estimate item costs or for various estimate subtotals. The values replaced could also be at the estimate element level such as quantities, productivity, item pricing, and so on, rather than for estimate item totals. This RP describes typical estimate breakdown variations with specific consideration of the need to address MCS correlation which becomes more challenging as more distributions are assigned. In addition to the topic of correlation, the RP also discusses MCS considerations for distribution assignment and determination of 3-point values; however, this RP is not a detailed treatment of MCS.

Contributors:

John K. Hollmann, PE CCP CEP DRMP FAACE Hon. Life (Primary Contributor)
Peter R. Bredehoeft, Jr. CEP FAACE
Colin H. Cropley
Francisco Cruz Moreno, PE
Larry R. Dysert, CCP CEP DRMP FAACE Hon. Life
Dr. David Hulett, FAACE
Sagar B. Khadka, CCP DRMP PSP FAACE
Luis Henrique Martinez
Martin Snyman, DRMP
Robert F. Wells, CEP

About John:

John joined AACE in 1986 and is a passionate leader in the cost engineering field, holding multiple certifications from AACE (CCP, CEP, and DRMP). He has authored and contributed to numerous AACE recommended practices plus many papers and led development of AACE’s Decision and Risk Management Professional (DRMP) certification.  He was the principal author of the first edition of AACE’s 2006 landmark publication The Total Cost Management Framework: An Integrated Approach to Portfolio, Program, and Project Management and also authored the publication Project Risk Quantification: A Practitioners Guide to Realistic Cost and Schedule Risk Management in 2016.

John has served AACE in various roles including chairs of multiple technical subcommittees. He was elected to and served on AACE’s Board of Directors for one year (1996-1997) where he was instrumental in the reorganization of the Board to create three Associate Boards (Technical/Education/Certification). John was a member of the Technical Board for several years where he served as Director of Recommended Practices and Director of Total Cost Management.

He has previously been recognized by AACE with the Outstanding Technical Committee Chair Award (1994, 1996), O.T. Zimmerman Founder’s Award (2005), Fellow (2006), Award of Merit (2008), Technical Excellence (2010), Honorary Life Membership (2011), the Lifetime Achievement Award (2018), and the TCM Excellence Award (2022).

John helps companies improve their cost engineering competencies and capabilities by evaluating processes, organization, tools and practices for cost engineering related functionality; assisting in implementing practice improvements; validating and reviewing major project estimates; performing risk analyses, contingency and escalation estimates; and by developing and conducting training.

He is currently the owner of Validation Estimating, LLC and alliance partner in ValidRisk.

AACE Members may download the RP free of charge here:
https://web.aacei.org/docs/default-source/rps/118R-21.pdf

Non-members may purchase the RP for USD 100 here:
https://www.pathlms.com/aace/courses/2928/documents/70494

Rate this post

Click on a star to rate it!

Average rating 4.7 / 5. Vote count: 3

No votes so far! Be the first to rate this post.

Leave a Comment

Your email address will not be published. Required fields are marked *